Freeway expansions value-engineered out of Interstate Bridge Replacement project, for now

Washington Governor Bob Ferguson at a press conference in Vancouver earlier today. (Screenshot from KGW live feed)

At a press conference in Vancouver today, Washington Governor Bob Ferguson announced that the Interstate Bridge Replacement Program will finally live up to its name.

Instead of five miles of freeway expansions and seven new interchanges, the project will be phased to include just the bridge replacements and an extension of MAX light rail across the Columbia River. Also making the cut in this “core set of projects” is the shared-use paths that will give bicycle riders and walkers new connections across the river.

Yes, project officials have finally relented and have decided to right-size the project in the way dozens of environmental and social justice organizations in the Just Crossing Alliance have been encouraging them to do for years now.

Advocates for a smaller IBR project outside the capitol in April 2023. (State Senator Khanh Pham in middle to left of sign. Photo: Jonathan Maus/BikePortland)

Ferguson also revealed a $7.65 billion cost estimate for this smaller project and said he’ll personally ensure construction begins by 2028. That’s still not a guarantee because the project has just $5.5 billion committed to the project so far. According to new cost estimate documentation shared today, that amount is enough for them to begin the major elements of the core set of projects.

“The first thing I want to say is we’re going to build this bridge,” Ferguson said at the outset of today’s press conference. “That’s going to happen. There’s just far too much at stake for any other option” Ferguson, flanked at the podium by project leaders, elected officials, and construction workers in helmets and hi-viz vests sought to tamp down skepticism of the project after a bombshell report by the Oregon Journalism Project back earlier this year that the full project would cost $12 billion to $17 billion.

New doc outlining “core set of projects” shared today that confirms inclusion of “enhanced shared-use path for people who walk bike and roll.”

That cost estimate, which project officials dismissed as being just a draft when that report came out in January, was confirmed by project officials today. The new, official estimate for the full, five-mile corridor is now $14.4 billion.

The full project is still on the table, but Ferguson made it clear that it’s being pushed back for now. “We will continue to work toward the larger corridor down the road, in phases, as funding becomes available,” he said.

TriMet General Manager Sam Desue was also at the press conference. In his comments he touted light rail’s first extension into Washington as opening up, “one seat ride from Evergreen into downtown Vancouver to downtown Portland, the Moda center, shopping, health care and so much more.”

Current conditions going southbound from Vancouver.

Toward the end of the press conference, someone in the media asked Governor Ferguson why the project had to include light rail at all, especially since many people in Clark County don’t want it. “That train has left the station,” Ferguson replied, without skipping a beat. “I want to be clear,” he continued. “I’m not interested looking backwards. We’re building this damn bridge. That’s happening, okay?!”

Ferguson’s enthusiasm is music to the ears of IBR project backers. But he’s only been on the job for 14 months and he’s also smart enough to understand that this project has been anything but easy since it first began in 2007. “We’re gonna have good days and we’re gonna have bad days ahead,” he cautioned folks at today’s presser (which included Portland Metro Chamber President Andrew Hoan, Oregon Trucking Association President Jana Jarvis, and many others). “That’s the fact. But I just want to be really, really clear that I’m super committed to this.”

Jonathan Maus (Publisher/Editor)

Jonathan Maus (Publisher/Editor)

Founder of BikePortland (in 2005). Father of three. North Portlander. Basketball lover. Car driver. If you have questions or feedback about this site or my work, contact me via email at maus.jonathan@gmail.com, or phone/text at 503-706-8804. Also, if you read and appreciate this site, please become a paying subscriber.

Thanks for reading.

BikePortland has served this community with independent community journalism since 2005. We rely on subscriptions from readers like you to survive. Your financial support is vital in keeping this valuable resource alive and well.

Please subscribe today to strengthen and expand our work.

Subscribe
Notify of
guest

5 Comments
oldest
newest most voted
Inline Feedbacks
View all comments
maxD
maxD
51 minutes ago

this sounds good, but I have so many questions: If we are just rebuilding the bridges, does that means we are keeping the lift/drawbridge? Would that mean the immersed tube is on the table? Are the MAX and bike/ped connections being considered as part of the bridge or as separate structures?

Coincidentally, I read this article this morning: https://www.clarkcountytoday.com/opinion/opinion-i-5-bridge-replacement-project-does-not-accomplish-the-needs-of-the-project/

Michael
Michael
17 minutes ago
Reply to  maxD

The one-sheet Jonathan included in the article explicitly states that the “main span” project will be two new fixed-span bridges.

Dave
Dave
21 minutes ago

I’d love to see them keep the current bridge for bikes, Max and pedestrians while moving cars to a tunnel. According to the guy advocating for it, Bob Orbland, he says it would be cheaper. Time to reevaluate?

Michael
Michael
13 minutes ago

This strikes me as nothing but good news. I still see the added auxiliary lanes as likely superfluous, but probably a necessary compromise to get the Yellow Line into Washington and largely mitigated by the inclusion of dynamic tolling.

Funny what happens when the high cost of inefficient transportation infrastructure catches up to you.

rick
rick
4 minutes ago

Does this mean the Columbia Slough bridge will be replaced? It currently seems like a good bridge even though it has pedestrian access only on the eastside. I don’t think it needs replacement.