On the ground with ODOT: Recap of I-5 Rose Quarter project bike ride

(photo Emily Guise)
The bike tour during a stop at NE Rodney and Tillamook.
(Photo: Emily Guise)

(Text by Emily Guise and Catie Gould, photos by Ted Timmons)

On a bright and showery Saturday morning this past weekend, ODOT hosted biking and walking tours of the changes planned to go with the I-5 Rose Quarter Project. ODOT officials including Region 1 Planner Megan Channell and Transit and Active Transportation Liaison Jessica Horning teamed up with Doug Zenn, a consultant for HDR, Inc. (a construction firm) to lead a bike tour of the area, while other ODOT staffers led a walking tour.

This was a great opportunity for a hands-on look at the proposed surface street changes we shared in detail on Friday. Here’s what we saw and learned…

Flint Avenue Bridge

(photo Ted Timmons)
A stop on Flint.
(Photo: Ted Timmons)

Channell admitted that ODOT hasn’t evaluated the approaches to see if it could meet [ADA] requirements.

About 15 people pedaled out of the Stingray Cafe parking lot and headed north on Flint Ave to the first stop of the ride. To accommodate the highway widening, this bridge is scheduled to be removed, and new bridge to replace it will be built running east-west to connect N Dixon and N Hancock St. Flint Ave will end at Tillamook St and southbound riders will have to use N. Vancouver Ave.

A participant asked if the project is about increasing connectivity, why trade one street for another? ODOT’s rationale for the new Hancock-Dixon Bridge is that the area is lacking in east-west connections compared to north-south. Taking out Flint Ave was part of the 2012 plans and has not been changed since. The Hancock-Dixon Bridge is far enough south of Flint that the both could feasibly exist and would provide more options for moving around the area.

The Hancock-Dixon Bridge wouldn’t be a direct connection to the Broadway Bridge, as it would direct a person on a bike onto Dixon, which parallels Broadway, and then another turn would be needed to get back onto Broadway.

There’s significant elevation difference on the two sides of the highway that the bridge would have to span. Upon being asked by Chris Smith, Portland Planning Commissioner, if the grade would meet ADA requirements of a 5% grade, Channell admitted that ODOT hasn’t evaluated the approaches to see if it could meet these requirements.

Highway Covers

(photo Ted Timmons)
Poster showing the Clackamas/Ramsay Way bridge crossing. Note the side profile showing 9 lanes.

The cost of the covers are included into the walking and biking improvements.

Many people asked about the highway caps, which ODOT labelled as highway covers. The current design shows two irregularly shaped covers instead of a continuous one spanning multiple blocks. ODOT explained that freeway covers over 800 feet long are considered tunnels and triggers additional regulations including: new restrictions on the movement of hazardous materials, additional ventilation, and height requirements.

Currently the covers planned won’t be able to support the weight of buildings and are designated as public park or plaza space. To support the additional weight of new buildings, Channell said covers would need deeper foundations and a taller structure, creating more community impacts. ODOT did not provide numbers about how much taller the covers would need to be or their cost.

The cost of the covers are included into the walking and biking improvements, which are considered local. ODOT will be paying for the columns and highway widening. Channell claimed that the $450 million will be split 50/50 between bike and walk improvements and the highway, but at this point there is still no official breakdown of costs.

Wheeler Ave and Clackamas Bridge

(photo Ted Timmons)
Looking east where the Clackamas Street bridge would come through.

Next, we rolled over to the intersection of NE Wheeler Ave, N Winning Way, and N Williams Ave, right by the I-5 on-ramp, where the western landing for the proposed Clackamas biking and walking bridge would be. The new connection into the Lloyd would be more modern and wider than older carfree bridges like the ones currently at Failing or Bryant streets, although there is no bridge design to show yet. There is no determination at this time if emergency vehicles could use this route, according to ODOT.

The current I-5 South on-ramp would be relocated northward to NE Weidler St. ODOT engineers say that removing the on-ramp will shorten the number of blocks people will have to drive to get to the ramp, and should reduce the number of turns people are making in the area, thereby reducing congestion.

No cover is planned in this area since I-5 is so close to grade level. To implement a cover, the road would have to be sunk to make enough clearance. The number of lanes to cross would increase to 8 (freeway and ramp) from 5 in the current configuration.

Advertisement

N. Williams Ave

Since this was planned in 2012 before the Williams bike lane shifted over to the left, it may need to be re-designed.

Continuing north on N. Williams, other significant changes are planned here. The block of Williams between Wheeler and N. Weidler is planned to be a bike, walk, and transit space only, with a short stretch open so that residents of the Madrona Studios will be able to access the parking garage there. There is a planned raised 2-way cycletrack on Williams on the block between Weidler and Broadway, but since this was planned in 2012 before the Williams bike lane shifted over to the left, it may need to be re-designed.

In that same block on Williams between Broadway and Weidler, a new lane southbound for cars queuing up for the southbound on ramp is planned. This lane is shorter than the previous 3 block loop but as Channell pointed out, the ramp is longer than before.

The land in the block immediately adjacent, bounded by Williams, Weidler, Broadway and NE Victoria Ave, is planned to be completely covered by a highway cover. ODOT proposes to turn it into a park or public plaza. Currently a Sherwin-Williams store sits on the site, which ODOT is negotiating to buy. Streets surrounding this block are on and off ramps for the freeway, so a a challenge is that people walking would have to cross significant vehicle traffic to access the public space.

Improved bike facilities for Broadway and Wielder were discussed but it was noted that the latest Broadway Plan was written in 1997 and hasn’t been updated since. Ride participants noted that improvements to bike infrastructure on Broadway and Weidler would be necessary to reduce conflicts with highway bound vehicles.

Rodney Ave

On Rodney, it was just a short stop. Since it parallels N. Williams and N. Vancouver, NE Rodney Ave will see an improved connection from the Hancock Dixon Bridge.

NE Clackamas from the Lloyd side

(photo Ted Timmons)
Looking west where the Clackamas Street bridge would be placed.

The eastern landing for the Clackamas bike and ped bridge will be in the last lane of the Crowne Plaza hotel parking lot and will then connect with NE 2nd Avenue. This uses a right-of-way that the city already has, though it will take parking away from Legacy Health.

(photo Ted Timmons)
Looking down at the existing I-5 corridor.

(photo Ted Timmons)
Looking down at the existing I-5 corridor.

Takeaways

ODOT repeated throughout the tour that the bike and ped plans are only 5-10% complete and they are looking for feedback. They are currently working off of the plan that came out of the 2012 design process.

The project will be undergoing an Environmental Assessment which will take 1.5 years to complete (next summer). Upon completion there will be more public comment periods and possible further environmental studies depending on the findings.

— Emily Guise and Catie Gould (text), Ted Timmons (photos)

Never miss a story. Sign-up for the daily BP Headlines email.

BikePortland needs your support.

Thanks for reading.

BikePortland has served this community with independent community journalism since 2005. We rely on subscriptions from readers like you to survive. Your financial support is vital in keeping this valuable resource alive and well.

Please subscribe today to strengthen and expand our work.

Subscribe
Notify of
guest

15 Comments
oldest
newest most voted
Inline Feedbacks
View all comments
Ted Timmons (Contributor)

One of my favorite moments, pasted from my notes:

Why are we working on car improvements so much?
(Maurice: ummmmmm, it’ll speed up the streetcar? And bikes?)

Spiffy
7 years ago

need to just close those on/off ramps…

wsbob
wsbob
7 years ago

The info on the covers (what people in comments to previous stories here have been mostly been referring to as ‘lids’.), is very interesting to me:

“…Many people asked about the highway caps, which ODOT labelled as highway covers. The current design shows two irregularly shaped covers instead of a continuous one spanning multiple blocks. ODOT explained that freeway covers over 800 feet long are considered tunnels and triggers additional regulations including: new restrictions on the movement of hazardous materials, additional ventilation, and height requirements.

Currently the covers planned won’t be able to support the weight of buildings and are designated as public park or plaza space. To support the additional weight of new buildings, Channell said covers would need deeper foundations and a taller structure, creating more community impacts. ODOT did not provide numbers about how much taller the covers would need to be or their cost.

The cost of the covers are included into the walking and biking improvements, which are considered local. ODOT will be paying for the columns and highway widening. Channell claimed that the $450 million will be split 50/50 between bike and walk improvements and the highway, but at this point there is still no official breakdown of costs. …” bikeportland

This answers questions people have had about why the covers have not been designed as one continuous unit. Also, why the covers as currently planned, aren’t sufficient to support buildings. At the least, some kind of rough idea from ODOT of what cost and difficulty of providing covers substantially strong enough to support buildings, might be a good idea to have the agency produce. This being a long, expensive project, better to consider all options now.

rick
rick
7 years ago

Build a freeway cap. Not more car lanes !

MaxD
MaxD
7 years ago

Those Freeway lids will not become parks. This is blatant greenwashing and ODOT should be called out on it right away! In order to grow trees in this condition, the structure would need to be able to support a minimum of 5-depth of saturated soil by approximately 10′ x 10′ plus the live load of a mature tree. In addition to the additional structural and drainage requirements, trees, shrubs and groundcovers would absolutely need permanent irrigation to survive Portland summers. Without being connected to the earth to maintain a minimal level of moisture, these planters would be become bone dry within weeks of no rain, low humidity and temps in the 90’s. To keep plants alive, even the most drought-tolerant species would need some water every 2 weeks. There is absolutely not any money in the maintenance budget of ODOT, PBOT, or PP&R for this. I would suggest getting ODOT to provide a detailed agreement of how they are paying for ongoing irrigation before letting continue to lie about adding park space. I hope someone can prove me wrong about this.

Paul
Paul
7 years ago
Reply to  MaxD

Maybe some type of park that does not include plants?

MaxD
MaxD
7 years ago
Reply to  Paul

like a Park and Ride? Just kidding, sort of. This could be a plaza, but it will be very difficult to activate since it is pretty cut-off by very large streets and not associated with a building or pedestrian amenity or thoroughfare. Also, It will be very loud due to being on top of a freeway and surrounded by busy surface streets. Too exposed for a contemplative space, too isolated for an effective plaza. This is not a useful public amenity- especially considering the price. I am sure that thoughtful design could create something of marginal use that will look good in photograph, but this strikes me as more greenwashing, as in “Portland pedestrians get our leftover staging space over the highway…you can use it as a park!” This is not entirely useless space- Portland NEEDS more public openspace. However, it should be noted now that is is extremely low-quality openspace that is being offered at an enormous price and cost (public health, etc)

Paul
Paul
7 years ago
Reply to  MaxD

No argument.

maccoinnich
7 years ago

“The eastern landing for the Clackamas bike and ped bridge will be in the last lane of the Crowne Plaza hotel parking lot and will then connect with NE 2nd Avenue. This uses a right-of-way that the city already has, though it will take parking away from Legacy Health.”

According the county assessor maps this ROW was vacated 50 years ago, and is now owned by Legacy. The parking lot was rebuilt with new landscaping, stormwater facilities and lighting only two years ago. Has Legacy agreed to sell this land to ODOT? Or are ODOT planning on using eminent domain? Assuming Legacy wants to keep the parking it has (a fair assumption, given that they just built it) how and where is ODOT planning on replacing it?

Nick Fox
Nick Fox
7 years ago

I’m grateful for the coverage you all are doing. Since this plan has been announced, I’ve seriously been sort of agnostic about adding the lanes to the freeway. I get it. I wouldn’t do it if I were in charge, but many people use private motor vehicles. Many people rely on shipping that relies on I-5.

But… after reading Michael’s and Emily’s coverage (thank you), I just can’t believe this is really a bike/ped project. And I ride and walk (and drive) through this area daily. There are spots for improvement. But I just don’t see how *any* of these major changes will be improvements worth the cost for pedestrians or bikes. It’s disappointing.

Mike Sanders
Mike Sanders
7 years ago

The interesting part of the bit about the covers is that they can’t be built as one unit because doing that would trigger hazmat regulations. In other words, a full cover would be classified as a Tunnel, and that means hazmats couldn’t travel under B’way on I-5. Instead, they’d have to exit at B’way and follow Williams Av. for several blocks. (This is why hazmats can’t use the Vista Ridge Tunnel and have to use SW Jefferson St. instead.) And southbound hazmats would have to exit at B’way as well, going downtown to connect to I-5 via the B’way Bridge or MLK/99E to get to I-84 eastbound. So do we trade hazmat traffic on local streets for ped/bike infrastructure?

wsbob
wsbob
7 years ago
Reply to  Mike Sanders

The covers can be built with additional ventilation to handle hazardous materials, depending I suppose, on what are the hazardous materials. Diesel truck exhaust is some of the most noxious exhaust on the road. Maybe I’m mistaken, but it seems that plenty diesel trucks are driven through the Vista tunnels. The tunnel walls certainly get coated with soot from motor vehicle exhaust.

“…ODOT explained that freeway covers over 800 feet long are considered tunnels and triggers additional regulations including: new restrictions on the movement of hazardous materials, additional ventilation, and height requirements. …” guise/bikeportland

Doug Klotz
Doug Klotz
7 years ago

Thanks Emily for the well-written article, and to Catie and Ted. When, at the open house, I asked for about heavier (taller) girders to support a useful lid, ODOT said that would mean raising the lids up, and ramping all surface streets up to that point. I asked why they wouldn’t just lower the freeway, and they said that “we’re not touching the freeway, except adding a lane on the side”. So, as MaxD points out, the lids/caps/covers are just “staging space”, where temporary street routes will go.

It may be fair to say that 50% of the project budget is to rebuild the street bridges and all the roadways over the freeway (plus that Clackamas bridge) but it is disingenuous of ODOT to claim 50% is going to ped and bike facilities.

Evan
Evan
7 years ago

How much would it cost to do the new bridges & caps/covers/lids without widening to 9 lanes?