(Photos: Jonathan Maus)
“We’re definitely learning some lessons.”
— Scott Cohen, PBOT project manager
It’s been six weeks since the Portland Bureau of Transportation (PBOT) began grinding off pavement and laying down new lane striping as part of the North Rosa Parks Way project. Yet despite weeks of dry weather and no major controversy or pushback (at least that we’ve been able to confirm), the project is still not closed to being finished. Meanwhile, people who ride on the two-mile stretch between Martin Luther King Jr and Willamette boulevards are frustrated by incomplete striping and many people park their cars illegally in the new bike lanes.
At the end of May, PBOT posted an update that acknowledged the major elements of the project that remain: they haven’t even began on the sections from Delaware to Interstate and Williams to MLK; none of the promised, plastic delineator posts have been installed; no permanent “No Parking” signage has been added despite a major change in parking availability; many bits of pavement markings are incomplete; and a median island crossing at Villard has yet to be started on.