The Marine Drive Path is 75% complete. Here are the gaps that remain


It’s easy to smile while riding on completed sections of the Marine Drive Path. Solid progress has been made recently and just six of its 23 miles remain.

The pandemic has reminded all of us how important it is to have safe network of off-street bike paths. After all, where would Portland’s collective mental health be today without being able to ride bikes free from the stress that some car users cause?

Original map of 40-Mile Loop taken from 1983 master plan. Red line is Marine Drive Path.

Some of the most popular low-stress places to ride a bike in Portland are along the 40-Mile Loop, a network of paved paths that circumnavigate Portland and that was first conceived by the Olmsted Brothers in 1903 as a way to connect the metro region’s parks. Unfortunately the “loop” part of the name is a bit of a misnomer because you can’t actually ride the entire thing. Last week, members of the 40-Mile Loop Land Trust held a meeting with Metro to provide an update on the remaining gaps. One of the stars of the presentation was the Marine Drive Path. (Note: I prefer “path” over more commonly used “trail,” because I think it’s less confusing to most people when describing paved facilities.)

The Marine Drive Path was first conceived in 1972 and is the region’s oldest path. When completed, it will run east-to-west for 23 miles between Kelley Point Park in north Portland to Depot Park in Troutdale. The path is extremely popular and is a key connection to I-205, several industrial corridors, and it’s the main gateway to the Columbia River Gorge. Currently about 17.5 miles are done and just under six miles remain to be paved and connected.

(Slide: Jim Sjulin/40 Mile Loop Land Trust)

At the meeting last week, volunteers and agency leaders working with the 40-Mile Loop Land Trust detailed the remaining gaps. I’ll detail them below from west to east.

Kelley Point Park (0.26 miles)

Sad signage near Kelley Point Park. (By the way, a true loop should never end.)
(Photo: Jonathan Maus/BikePortland)

This one should be a no-brainer. Right now a paved path inside Kelley Point Park stops just a quarter-mile from another paved path that goes under North Lombard along the Columbia Slough. The path is engineered and all planned out. All that’s missing is funding. This gap is especially problematic because it leads many people to cross a section of N Marine Drive with poor sight lines that’s also a major freight corridor with relatively high traffic speeds.

Bridgeton (0.57 miles)

(Slide: Jim Sjulin/40-Mile Loop Land Trust)

Bridgeton is a community along the Columbia River east of I-5 and north of Marine Drive. According to resident and 40-Mile Loop Land Trust volunteer Walter Valenta, the only reason a gap in the path remains through this section is due to one property owner who’s unwilling to sell an easement. “We’re stuck until we can get the right to build the trail,” he said. This gap forces riders onto Marine Drive where there’s very little space to operate. This is one of the most harrowing sections of the route.

East Columbia (1 mile)

(Slide: Jim Sjulin/40-Mile Loop Land Trust)

This gap, from about 13th Avenue to 33rd (adjacent to Columbia Edgewater Country Club), is currently in flux. Possible development of the Port of Portland property on the east end gives advocates hope and recent work from PBOT on the intersection with 33rd has created more urgency as well. Parts of this gap could be a candidate for funding through a federal program to improve the levee that it sits on. The western segment along the country club will be more challenging.

Parkrose (0.9 miles)

(Slide: Jim Sjulin/40-Mile Loop Land Trust)

Starting at I-205 and heading east to 122nd, this gap has been made a bit easier to swallow thanks to wider bike lanes recently installed by PBOT. A new signal at 122nd has also helped calm drivers down a bit. But a path would be much safer for more types of riders. The plan is to keep continue the path on the north side of Marine Drive along the river and then build a new crossing just west of 122nd. The good news is easements have been secure and all that’s needed is funding.

Gresham (0.7 miles)

Purple lines show existing gap (left) and section to be rebuilt (right). (Source: Mel Huie/Metro)
Crossing plans.
(Source: Metro)

Metro is taking the lead to close the gap from NE 185th to Interlachen Lane (Blue Lake Park). They also plan to rebuild a bumpy and cracked section of existing path that starts at Blue Lake Road and goes 0.6 miles to NE 223rd. Metro planner Mel Huie says they’ve got $2.85 million set aside for the projects and they’ll be completed by spring of 2023. Huie also shared that the Fairview-Troutdale project (below) will include a new signalized crossing of Marine Drive from Metro’s path near Blue Lake Park (at right).

Fairview-Troutdale (1.6 miles)

(Source: Port of Portland)

We reported on this exciting project back in 2016. It will pave a new, 10-foot wide path from a new crossing at NE 223rd that will follow the Columbia River to an existing path path that starts just west of the Sandy River Delta area. The Port of Portland and City of Troutdale will also build another piece of path along the river to connect to the existing path under I-84 north of Troutdale via Harlow Road. When complete, you’ll be able to completely avoid the stressful I-84 ramps and truck stop section and remain on a low-stress path to connect to the Historic Columbia River Highway. Design on this project was completed in 2019 and a rep for the project said construction will start in fall 2021.

Depot Park (0.3 miles)

(Source: City of Troutdale)

The City of Troutdale is taking the lead on this final piece of the path that will eventually be not just the eastern end of the Marine Drive path, but will also serve as the western hub of the Historic Columbia River Highway State Trail (which is getting very close to closing its final gaps too). From last week’s meeting it sounds like Troutdale has an exciting plan underway. Troutdale Community Development Director Chris Damgen said a new, 12-foot wide path will connect to the existing I-84 bridge path and head south (on the west side of the Sandy River) along a currently undeveloped parcel. The path will go along a high embankment with “really spectacular views” of the Sandy River Canyon. It will go under the railroad trestle and then cross the Historic Highway at Glen Otto Park. It’s scheduled for completion within the next 2-3 years.


The 40-Mile Loop Master Plan was published in 1983, that means it will celebrate its big 4-0 in just two short years. Hopefully by that time we can have a big — gap-free — ride around the entire loop! Stay tuned for news and action alerts to help this effort get across the finish line.

— Jonathan Maus: (503) 706-8804, @jonathan_maus on Twitter and jonathan@bikeportland.org
— Get our headlines delivered to your inbox.
— Support this independent community media outlet with a one-time contribution or monthly subscription.

Switch to Desktop View with Comments