PBOT: Nine Central City bike and transit projects will break ground in 2022


No more sharing the lanes on SW 4th once the new bikeway is built!
(Photo: Jonathan Maus/BikePortland)

“Protecting buses from traffic delays makes buses a logical choice for more people… even though these are small segments, they mean big improvements in reliability for transit.”
— Jarrett Walker, transit consultant

The Portland Bureau of Transportation (PBOT) has just announced that it will begin construction on nine projects in 2022 that have emerged from their Central City in Motion and Rose Lane Project plans.

According to a PBOT press release, these nine new projects will be “designed to improve the speed and reliability of transit, provide dedicated space for people who bike, and… make streets safer regardless of how you travel.”

One project announced as part of this construction plan is the highly-anticipated Southwest 4th Avenue Improvement Project. A new fly-over video (below) shows details of what SW 4th Ave from SW Lincoln to W Burnside Streets will look like when this project is complete: there will be a new concrete bus and turn lane — and accompanying floating transit island — to to reduce delays for riders on TriMet lines 9, 12, 17, 43 and 44, improved street lighting and, notably, a left-running protected bikeway on a street that currently has no dedicated space for cycling. PBOT says this construction project will begin in summer 2022 and last about a year.

YouTube video player

Here are the other projects (descriptions via PBOT):

Advertisement

SW Alder Rose Lane Project

A rendering of the SW Alder Street Rose Lane Project, looking east. (Source PBOT)

This project supports TriMet’s line 15 route change, which will move the eastbound bus from SW Salmon Street to SW Alder Street to reduce travel time and simplify the route. Improvements on SW Alder Street will feature in-lane bus stops and transit priority improvements. The project will result in on-street parking and loading zone changes. This project is scheduled to begin construction this spring and be complete by May 2022.

SW Jefferson Bus and Bike Improvements
This project will improve transit and upgrade bike lanes on SW Jefferson Street between SW 14th and 18th avenues (Collins Circle), decreasing delays for riders on TriMet lines 6, 45, 55, 58, and 68. The project will result in on-street parking and loading zone changes. Construction on SW Jefferson is scheduled to begin in spring 2022 and will last approximately two months.

SW Broadway Bike Improvements
This project will improve bicycling along this important north-south corridor. Improvements include protected bike lanes between SW Oak and Clay streets, signal improvements, and parking changes to better serve passenger and food pick-up and drop-off. Construction on SW Broadway is scheduled to begin in summer 2022 and will last approximately four months.

W Burnside Bus Lane Improvements
This project will improve speed and reliability for eastbound transit riders along W Burnside from 8th to 3rd avenues. The new bus lane will benefit the thousands of Portlanders who travel on TriMet lines 12, 19, and 20. As part of the changes to West Burnside, two eastbound general-purpose lanes will be maintained, while left turns from Burnside to 4th Avenue will be prohibited. Construction on W Burnside is scheduled to begin in summer 2022 and will last approximately one month.

NE Couch Rose Lane Project
This project will improve speed and reliability for westbound bus riders on TriMet lines 12, 19, and 20 by creating a new Bus and Turn lane along NE Couch Street from NE 12th Avenue to NE 7th Avenue. The project will upgrade traffic signal timing to better manage traffic flow westbound and will also provide a bike connection along NE 7th Avenue between SE Washington Street and the Blumenauer Bridge. Construction on NE Couch is scheduled to begin in summer 2022 and will last approximately two months.

E Burnside Bus and Bike Improvements

A rendering of East Burnside at NE Martin Luther King Jr. Boulevard, looking east. (Source: PBOT)

This project will improve speed and reliability for eastbound transit riders along E Burnside from MLK to 12th Avenue through the conversion of one of E Burnside’s general-purpose lanes to a bus and turn lane. The new bus lane will benefit the thousands of Portlanders who travel on TriMet lines 12, 19, and 20. A new traffic signal will also be installed at E Burnside and MLK to improve safety. Construction is scheduled to begin in the summer of 2022 and last approximately 12 months.

Central Eastside Access and Circulation Improvements
This project will improve freight access and circulation and reduce multimodal conflicts in the Central Eastside through the installation of a series of new traffic signals (see map). Benefits of the new signals range from improving freight access to I-84 via a new traffic signal at NE Irving and 16th to creating a safer connections for pedestrians and cyclists through the Central Eastside to the Esplanade via new crossings of Martin Luther King Jr. Blvd. and Grand Avenue at Salmon Street. At each location, ADA accessible curb ramps will be installed alongside high visibility pedestrian crossings and bicycle connections to existing bike routes. Construction is scheduled to begin in the summer of 2022 and last approximately 12 months.

Hawthorne Viaduct Bus Implementation
This project will improve transit speed and reliability on the Hawthorne Viaduct on the east end of the Hawthorne Bridge, extending the eastbound bus-only lane along the viaduct in partnership with Multnomah County. This work is part of a larger effort to improve transit speed and reliability along SE Hawthorne, with the section of SE Hawthorne between Grand and 12th avenues completed this past summer and a new BAT lane added at SE Hawthorne Boulevard and Cesar Chavez this past fall. Construction is scheduled to begin in spring 2022 and will last approximately one month.

With major improvements already progressing nicely on Naito, this is more great news!

Having functioning transit service in Central City is crucial now that more people are beginning to commute downtown again. PBOT hopes that these construction projects will help smooth out congestion in some of the busiest parts of the city.

Jarrett Walker, a public transit consultant who has worked with the city of Portland on the Rose Lanes Project to improve bus service, says that these bus lane improvement projects are necessary if we want more people to be riding the bus.

“Just as safe cycle facilities make people ride bikes more, protecting buses from traffic delays makes buses a logical choice for more people. While we need more bus lanes across the city, these downtown improvements are targeted at the worst bottlenecks.” Walker said to BikePortland. “So even though these are small segments, they mean big improvements in reliability for transit.”

Stay tuned for more detailed updates on these projects.