Terry Dublinksi-Milton is a Portland resident and dedicated neighborhood activist and transportation reformer. Last summer we shared his call to create an active transportation network in southeast.
I have worked on and critiqued multiple bikeways over the years and though a smaller bike project than many, I have a personal attachment to the NE 60th and Halsey Improvement project. This project is in my neighborhood of fifteen years and has its own history nearly as long.
That’s why it’s so important for me to get it right. Before I share my concerns on the project and feedback for how to make it better. Here’s a brief look in the rear-view mirror…
60th Avenue Station Plan (2007)
A series of outreach meetings in 2006-2007 developed the 60th station plan that proposed significant changes to local access, bikeways, and MAX light rail. Routes in the plan included NE Hassalo/53rd to 61st, 61st to Sacramento north, and Oregon/63rd to Davis south. For reasons lost to planner history, it was not adopted by council; but the bikeways made it into the Bike Plan for 2030 which was adopted in 2010.
Comprehensive Plan (2014-2017)
As Land Use & Transportation Chair chair of North Tabor Neighborhood Association I helped resurrect the 60th Ave Station Plan and through multiple outreach meetings moved the Tabor Trail to 62nd, extending it south to Mount Tabor Park. NE 61st remained, but a bikeway connection west to 47th, Providence Hospital and points further was added to the Comprehensive Plan.
Growing Transit Communities (2017)
In this refinement of the station area plan, the local access road building was removed in favor of a Vision Zero-compliant Halsey Blvd. The Tabor Trail remained on the same route outlined throughout the comprehensive plan.
Despite this long history, all it took was one community ride-along where a few people expressed discomfort with the hairpin turn at NE 61st (circled in red in graphic at right) caused PBOT to move the climb up Alameda Ridge to 60th. An engineering solution to 61st was not even suggested, thus this meandering alignment suddenly became the current proposal (outlined in yellow).
PBOT’s new route introduces two turns, requiring one to go west, then east, to go west.
Will a student from Madison High follow a route like this to the Waterfront?
While it’s the cheapest to build, plans for NE 60th offer no protection for bicycle users other than sharrows and speed bumps. While 60th has an average daily traffic (ADT, a stat that only includes car drivers) count of 1,040, 61st has only 400. The way I see it, PBOT is using bicycle riders to calm driving traffic, instead of diverting them away from the route to maintain a quality bikeway.
Another option would stay on 60th from the MAX station the entire way north (as PBOT proposes for just a few blocks in their current plans). Parking would be completely removed and replaced with a two way cycle-track and significantly wider sidewalks than proposed.
Advertisement
This second option has the benefit of being the most direct and predictable up the ridge for cross-traffic but provides no significant protection for the ascent. Option 2 requires a complete redesign of the NE 60th/Halsey intersection and removal of the center turn pockets. These center turn pockets are what requires the segment from Hassalo to Halsey to be moved to 62nd for queuing. The traffic lights were rebuilt last in 1984, do not allow for leading pedestrian intervals (LPIs), and are required to properly time the 57th and 60th signals which should speed up the 71 bus line.
This is by far the most expensive choice. It prioritizes walkers and bicycle users, but it also creates delays for transit and car users.
The final and original route follows a low volume 61st from Halsey to Sacramento. The main fear is the 10 mph hairpin switchback with poor sightlines.
To safely engineer this troublespot we could remove rarely used westside parking and convert the northbound lane into a physically-protected bike lane. The descent would consist of a shared, low-volume lane southbound. The switchback would make the climb easier than 60th without growling cars menacing at riders from behind. The new traffic pattern would only impact 12 households and 150 average daily driving trips and would have vast benefit to the active transportation network. Moderate in expense, it would provide a direct route and the only truly protected climb up Alameda Ridge just in time to coincide with a newly rebuilt Madison High School. The sidewalk-free side could be striped with a walkway and the one-way would mitigate head-on collision risk between vehicles, thus providing safety benefits for all three traffic modes simultaneously.
The 2007 plan called for a bioswale (a planted curb extension to soak up rainwater) at 61st and Sacramento to narrow the intersection which could become a rest area with maps of the entire Tabor Trail. In the near-term, wands could be used to protect the lane. This would have the added benefit of narrowing Sacramento, thereby calming two greenways. A bike lift — like the one used in Trondheim, Norway — could even be added as this is the only climb up Alameda Ridge without curb cut conflicts.
Providing a facility for all users regardless of ability, a lift would be an amazing amenity and become a local attraction. If PBOT is serious about getting young people to bike to school, this is the type of creative infrastructure we need. In our age of climate crises, we must use every tool possible to lower emissions.
Portland’s adopted plans make it clear that walkers and bicycle users are at the top of the transportation pyramid. This means new bikeways are to be protected when possible and direct even if it mildly disrupts single-occupancy vehicle users. In the case of NE 61st, we have an opportunity to improve safety for all traffic modes.
If you want to learn more, I’m leading a Pedalpalooza ride on Monday (6/17) to highlight the choices, investigate other proposed improvements and point to missing connections. PBOT representatives have promised to join us as we circle the station and climb the ridge.
Maxing Access to the MAX, a 60s Adventure
Monday June 17th 5pm, leave 5:15
Normandale Park, near the restrooms
60s Clothing Encouraged
The public comment period for the NE Halsey project closes June 24th, so let’s use this opportunity to get it right!