Site icon BikePortland

Springwater path closures coming in October

Buffered Bike Lane with a bike symbol and arrow pointing forward


PGE Work will close the Springwater in Gresham in October. Check out the official details below:

Gresham was notified recently that PGE will be closing a portion of the Springwater Trail as they replace insulators on their transmission lines. The closures will take place October 6 through October 10 and will run from 8 a.m. until 3:30 p.m. each day. I’m not sure if they will keep the trail portions closed after 3:30 or restage the closures daily.

The following is a list of the four trail segments to be closed, a map of each closure location and corresponding detour.
• SW Pleasant View Dr. to SW Towle
• SW Eastman Parkway to SW 7th St.
• SW 7th St. to SW Walters Dr.
• SW Walters Dr. to SE Park Dr.

James Chrisman – James.Chrisman@pgn.com, (503.736.5749) is the PGE contact for this project.

Switch to Desktop View with Comments