Behind the scenes of Capital Bikeshare


Behind the scenes at Capital Bikeshare-2
It doesn’t look like much, but behind these
doors is the nerve center for America’s premier
bikeshare system.
(Photos © J. Maus/BikePortland)

An unassuming warehouse in the industrial Navy Yards neighborhood of southeast Washington DC is the headquarters of America’s most successful and largest bikeshare system.

I’ve been using Capital Bikeshare for a week now and it’s fantastic. With Portland set to launch a similar system next year (hopefully), I wanted to find out what makes the system tick. So on Thursday I rented a bike from a station two blocks from where I was staying and pedaled toward the warehouse. I was met by Capital Bikeshare General Manager Eric Gilliland.

Behind the scenes at Capital Bikeshare-21-2
Capital Bikeshare GM Eric Gilliland.

When Capital Bikeshare launched in September 2010, it had 49 stations and 400 bikes. Today, Gilliland and his staff oversee 199 stations and 1,700 bikes that span throughout the DC region. (For context, Portland is aiming for 75 stations and 750 bikes and New York City is expected to launch in May with a whopping 600 stations and 10,000 bikes.)

The bikes and their stations have become a fixture on the streets of DC. They are part of the cityscape much like bus stops, taxis, or newsstands:

Washington DC-14
Washington DC-4
DC bike people-10
Day on a bike in DC-19
Bikeshare station at Whole Foods
Coverage from Washington D.C.
made possible by:

As former executive director of a local bike advocacy group, the Washington Area Bicyclist Association (WABA), Gilliland is no stranger to working around bikes. In many ways, his mission at WABA is similar to his task at Capital Bikeshare: Get more people on bikes. And Capital Bikeshare has done just that. Since 2010, the system has served 3.6 million rides, it now boasts over 20,000 members and it’s only public transit system in the U.S. that pays 100% of its operating costs through user fees (TriMet’s “farebox recovery” rate is just 25%). Key to the system’s success are DC’s many tourists, whom Gilliland says are “big revenue generators” because they tend to ride longer and don’t mind paying the extra fees (trips under 30 minutes are free).

Day on a bike in DC-51
Tourists roll on the Rock Creek Trail.

Unlike the forthcoming CitiBike system in New York City (which Citibank has sponsored to the tune of $41 million) and Portland Bike Share (still dreaming for a big sponsor) which are 100% privately funded, Capital Bikeshare is funded by federal grants and local governments.

When asked about funding models, Gilliland sees more a hybrid funding scheme as the best option. “We’re the opposite of New York City, but I think a middle ground would be good,” he said, “There’s a role for private funding, but it’s a transit system, so DOTs should play a role. It’s a public good you’re providing — it’s an investment in your city.”

The next step for Capital Bikeshare, Gilliland said, is to sell naming rights to a private sponsor (as evidenced by the image below which shows how the new front racks (on the left) have a spot for a sponsor’s advertisement):

Behind the scenes at Capital Bikeshare-31-2

While sponsorships and size tend to dominate the public dialogue around bike share, on Thursday I got to see the other side: the warehouse and workshop where a team of hard-working staff keeps the system up and running.

Behind the scenes at Capital Bikeshare-3
Bikes in need of a tune-up await their turn next to boxes of new bikes shipped from Public Bike Share Company in Montreal, Canada.
Behind the scenes at Capital Bikeshare-17-2
Keeping track of 1,700 bikes demands careful tagging.
Behind the scenes at Capital Bikeshare-7
Some of the service calls are made with cargo trikes.

Capital Bikeshare employs 45 people; a mix of managers, mechanics, technicians and a street team (technically they’re all employed by Alta Bicycle Share, the system’s operator).

Most of the staff at Capital Bikeshare is made up of what are known as “rebalancers.” They’re in charge of making sure there are just the right number of bikes at any one of the stations at any given time. The term “rebalance” is used because they attempt to balance out the empty and full stations so users are assured either a bike to rent or a place to dock no matter where or when they need one.

Unlike a subway or bus system, where the passenger vehicles rotate through the routes consistently, there’s a finite number of vehicles in a bikeshare system and a limited number of places to park them (each bike must be secured at an electronic docking station). And depending on topography, commute patterns, and special events — mass migrations of the bicycles from one part of town to another presents a challenge. The northwest part of DC, for example, is densely populated and it’s on a hill. This means in the morning, thousands of people grab bikeshare bikes and roll into downtown.

“In the morning, we try to have [downtown] stations empty,” explained Gilliland, “As they fill up, we sweep up the bikes and try to catch another wave of commuters.”

Day on a bike in DC-41
A sunny Saturday in the bikey and bustling Adams Morgan neighborhood left this station empty. (It was only empty for a few minutes.)

Big events like July 4th and sunny spring and summer days also put pressure on the rebalancing crew. On Saturday, as temps neared 60 degrees, 455 bikes were being used simultaneously. During a typical day, about 200 bikes will be out at any one time. The number of daily trips taken also varies greatly depending on the season and events. According to Gilliland, the system serves about 5,000 trips per day, with that number rising to 8,000 in peak season. They expect the first 10,000 trip day this summer.

Tracking how many bikes are available at any given station falls on the shoulders of Rebalancing Supervisor Alex Fuentes. At the 2nd Street headquarters on Thursday, Fuentes sat at a desk monitoring two computer screens. Staring at an online map that shows station locations and the number of bikes available, Fuentes held a dispatch phone in one hand and a computer mouse in the other. As the evening commute ramped up, he wanted to make sure there were enough bikes and enough empty spaces so customers wouldn’t run into any delays.

Behind the scenes at Capital Bikeshare-13-2
Rebalancing Supervisor Alex Fuentes.
Behind the scenes at Capital Bikeshare-12-2
The crew relies on mapping software for a real-time look at the system.

Rebalancing is important not just for customer service, but I learned Thursday that Capital Bikeshare’s operating contract with the District Department of Transportation stipulates they can be fined if any station is empty or full for more than an hour.

After staring at the computers intently, Fuentes picked up the dispatch phone and gave orders to one of his truck drivers: “Go to 17th, pick up five bikes. 18th and Penn pick up fives bikes. Go to 19th and L and drop off five bikes.”

Fuentes also manages the five Capital Bikeshare service trucks. The white Freightliner Sprinter trucks are operated on two shifts per day (leaving only a few hours when there aren’t staff on the streets).

Avoiding fines and keeping users happy falls on the shoulder of rebalancers like Javier Griffiths and Veltrick Copeland. After rolling a few bikes up the rear ramp of his truck, Griffiths, wearing a reflective vest with Capital Bikeshare emblazoned on the back, hopped into the cab, flipped open a laptop and headed out on a service call. I sat in the passenger seat as we rolled out to pick up bikes from two stations near Union Station.

Behind the scenes at Capital Bikeshare-26-2
Javier Griffiths at the wheel.
Behind the scenes at Capital Bikeshare-25-2
CaBi Tracker is a software program that tracks usage patterns and station data in real time.

“It’s a fun job,” he said, as we rolled out of the warehouse yard. “Sometimes I’ll see people at a full station with no place to park and they’ll get all excited when they see the truck pull up.” Like many people that work at Capital Bikeshare, Griffiths believes in bikes. A former bike messenger who grew up in DC. and sometimes takes bikeshare to work, he spoke of their many virtues: “Biking is usually the fastest way around town. You don’t have to worry about parking… I just love bikes. They’re the future.”

Behind the scenes at Capital Bikeshare-33-2
Behind the scenes at Capital Bikeshare-30-2
Behind the scenes at Capital Bikeshare-27-2
Behind the scenes at Capital Bikeshare-34-2

Capital Bikeshare’s contracts with the various jurisdictions they operate in requires bikes to be available, and it also requires that the bikes stay in good, working condition (technically, the contract says each bike in the system must be “touched” by an employee once per month). That job primarily falls to the six full-time mechanics on the staff. I watched one of them, Timur Mukhodinov, do an annual maintenance service. He replaced nearly all the main components; lights, tires, rack, fenders, kickstand, bell, and so on.

Behind the scenes at Capital Bikeshare-14-2
Timur Mukhodinov does an annual tune-up.
Behind the scenes at Capital Bikeshare-6
Behind the scenes at Capital Bikeshare-8
Behind the scenes at Capital Bikeshare-16-2

Across the warehouse from the mechanics’ workshop, Bike Checking Street Team Manager Taylor Jones, Deputy Operations Manger Mike Garrett and Technology Manager Ralph Lucas discussed an issue in the Station Service office.

Behind the scenes at Capital Bikeshare-9-2
Left to Right: Technology Manager Ralph Lucas, Deputy Operations Manger Mike Garrett, Bike Checking Street Team Manager Taylor Jones.

Similar to the rebalancing and mechanic crews, Capital Bikeshare is contractually obligated to keep the stations fully operable or they’ll be fined. The contract mandates that each station in the system is checked up on at least twice a month.

During my week of using the system, I never had a beat-up bike. And despite a sunny Saturday, I never had to wait or ride to a new station to rent or park a bike. It seems that, even in their infancy and with constant expansion plans, Capital Bikeshare is doing a great job managing this system. So much so that Gilliland and his crew have been sought out for their expertise. “We’ve sort of become a training academy for other cities. We had some folks from New York City in here last week.” said Gilliland.

It’s somewhat ironic that Gilliland, who once led a non-profit bike advocacy group, now oversees operations of a private company that might have even greater influence overy transportation policy in his city. The thousands of daily bikeshare users are also riding in bikeways that Gilliland helped push the city to build. And now Capital Bikeshare is doing the pushing. “All the people out riding on the bikes is forcing the City to do a better job,” explained Gilliland. “Overall, it’s been an amazing success.”

Capital Bikeshare by the numbers:
  • 45 people on staff
  • 61 reported crashes
  • 8,900 trips in one day (the record)
  • 3.6 million rides since September 2010
  • 25 bikes stolen
  • 11 stolen bikes recovered
  • 14 bikes lost
  • 10 bikes have had “extreme vandalism”
  • 6 full time mechanics
  • 25 rebalancers