A closer look at bikes and the Sellwood Bridge Project

Sellwood Bridge Project Citizen’s Task Force member Richard Marantz on the Sellwood Bridge.
(All photos: Jonathan Maus)

Last week I spent a day with Richard Marantz to get the lowdown on bicycle access issues in the Sellwood Bridge Project.

Richard is an avid bicyclist and member of the project’s Citizens Task Force. He is also acting as a volunteer liaison for the BTA (due to a staffing crunch, they were unable to devote paid staff.)

For those of you who haven’t heard, the 81 year-old Sellwood Bridge is in woeful shape and has been targeted for rehabilitation or replacement. Multnomah County owns the bridge and they are several years into a community process to determine the best options for the new bridge.

Sellwood Bridge Tour with Richard M.

Richard schooled me
on the Sellwood.

Before riding down to Sellwood for a closer look at the bridge, I met Richard on the Esplanade where he gave me an overview on where things stood with the project and how bicyclists were faring in the process.

Richard said that there are plenty of bicycle-friendly voices among the advocates and planners involved with the project. He also added that bicycles are a well-represented constituency. He cited one recent survey where 31% of respondents said they used a bicycle to cross the bridge.

I was pleased to hear Richard say he feels like Multnomah County and the professional consultants working on the project really “get it” when it comes to bicycle access. “To them,” he said, “this bridge is perceived as a clear link in the trail system and they’re treating it like a recreational asset… rather than simply painting some extra lines on the roadway.”

Richard laid out the project into three main components:

  • Alignment (where a new bridge would go)
  • Intersection design (how to design the streets on either end)
  • Bridge roadway design (lane/path configuration)

Alignment
This component has to do with deciding on where the bridge will physically go. Richard said it’s a “secondary concern” to bicyclists and that the actual design of the roadway (on the bridge) is more important.

Sellwood Bridge Tour with Richard M.-8

Regardless of which alignment is chosen,
some residences will be impacted.

Intersection design
This component deals with how to design the access streets and approaches to the bridge on either end. Richard says that most of the discussion has been centered on the west side. This is because of limited right-of-way (hilly terrain), the presence of a major arterial (highway 43) and the entrance to the Riverview Cemetery (which happens to be a popular shortcut for cyclists to the SW hills).

The two designs currently on the table for the west side intersections are a signalized intersection or a roundabout.

Richard says that for bike safety, the signalized option is preferred. He notes that for motorized vehicles the roundabout has a more “intuitive feel” (not having to stop), but he thinks signals will do a better job of balancing out traffic flow onto the bridge and will ulimately make for safer cycling.

Engineers on the project have said that both options net the same results for automobile congestion.

Sellwood Bridge Tour with Richard M.-10

Under the west end.
Sellwood Bridge Tour with Richard M.-2

Just north of the existing bridge,
Marantz explained various alignment options.

Bridge roadway design
Roadway design has to do with the number, width and configuration of the bike, car, and pedestrian travel lanes. There are currently 11 roadway design options currently being considered.

This is the most important component for bicyclists.

View some of the roadway
configuration options.
(Click to enlarge)

The roadway design options depend on whether the bridge is rehabilitated or replaced (both options are currently still being considered, although replacement seems more likely).

If the bridge is rehabilitated, the bike/ped access would either be cantilevered out (like the Hawthorne Bridge), or it would go underneath the trusses of the current bridge. Of these two options, a cantilevered bike/ped path is preferred. The underneath option is thought to be less secure (poor visibility) and the entry/exit connections would be more complicated.

The most exciting options for bike facilities are only possible if they replace the bridge.

These options have many configurations, from a shared path with widths ranging from 10-20′ and a total bridge width of 57-80′. Click the graphic above (and right) for a closer look at these options.

Richard says that in all the options, there is a strong effort to separate not just cars from bikes and peds, but also to separate bicyclists of varying speeds.

Of the 11 roadway configuration options currently on the table, the configuration below scored highest in a recent exercise:

This configuration scored highest in a recent options evaluation exercise.

Scoring of roadway design options
To help guide decision-making on the project, members of the Citizen’s Task Force were asked assign a certain number of points (weight) to various criteria. These included: bike/ped access; residential impact; environment; auto/freight access; etc…

Within each criterion, represented interests chose a subset of priorities. Richard says the bike/ped representatives on the Task Force chose two priorities in weighing their criterion: safety and connectivity (how the paths enter and exit the bridge span).

The next steps
From this point in the process, the decision makers will choose four bridge options that will go into the Draft Environmental Impact Statement (DEIS). Richard says the choices will likely include one “perfect bridge”, the highest scoring bridge in the Citizen’s Task Force evaluation, a low residential impact option, and a bridge rehabilitation option.

Other bike/ped issues
Leaving the current bridge as bike/ped only
Richard says this option is being looked at (read my story and the discussion on it from a few weeks ago) but that everyone who has taken a closer look realizes it is unlikely to happen. Even if the current bridge was re-purposed, it would require costly upgrades, and the ongoing cost and performance of maintenance is also a risky unknown.

Richard says there are also concerns that as a bike/ped only bridge it would have trouble competing for federal funds with other, higher volume bridges.

Other concerns about about having a separate bike/ped only bridge include;

  • Connectivity: how would people get from the old to the new bridge to catch a bus?
  • If the old bridge falls down, we have to settle with whatever bike/ped facilities exist on the new bridge.

In the end, Richard says we’re, “better off working for world-class bike facilities on the new bridge.” I agree. We need to focus more on mixing modes effectively and safely, not looking for ways to separate each other (which is not possible in many situations anyways).

A detour bridge during construction
Construction of the bridge is likely to last at least two years. The question is, will a detour bridge have to be built? And, if so, will it accommodate all users? Richard told me that early conversations about a temporary bridge did not include bike facilities. Concerned at this, Richard now says, “it has been duly noted that a detour bridge without bike facilities is not acceptable.”

Sellwood Bridge Tour with Richard M.-6

Narrow sidewalk and no shoulder.

Access to the Riverview Cemetery
There is currently a delicate balance of public access and private property rights relating to bicycles in Riverview Cemetery. The owners have proven very cooperative in allowing bikes to ride through their property (even though problems have arisen in the past). Richard says there are many issues to consider about continued Cemetery access.

  • If intersection design results in no more auto access at lower entrance (this is what ODOT prefers), than the owner might just close it to bikes as well.
  • If the rate of bike trips through the cemetery skyrockets with a new and improved bridge (Richard thinks it won’t, because new users will primarily be recreational and would choose a riverfront loop over a challenging hill), will it force renewed discussion over how to manage public access?
Sellwood Bridge Tour with Richard M.-5

Richard said they’ve kept cemetery bike access at the forefront “since day one in the process” but adds that his worst fear is that it ends up being worse (than now) in the end. Even though it’s private property, the route is currently listed on city bike maps and it provides a welcome shortcut for commuters and enthusiasts. However, it’s clear that when push comes to shove, the property owner is not going to go out of his way to accommodate bicyclists.

Richard Marantz is obviously very passionate about how bicycles fare in this long process and he’s doing a superb job representing our interests. We should all be grateful for his volunteer service.

Stay tuned for more coverage of the Sellwood Bridge Project as things progress. If you have questions about this project, leave them in the comments and Richard, myself, and other folks will try to answer them.

For more information, check out the very awesome Sellwood Bridge Project website.

Jonathan Maus (Publisher/Editor)

Jonathan Maus (Publisher/Editor)

Founder of BikePortland (in 2005). Father of three. North Portlander. Basketball lover. Car owner and driver. If you have questions or feedback about this site or my work, feel free to contact me at @jonathan_maus on Twitter, via email at maus.jonathan@gmail.com, or phone/text at 503-706-8804. Also, if you read and appreciate this site, please become a supporter.

Subscribe
Notify of
guest

12 Comments
oldest
newest most voted
Inline Feedbacks
View all comments
Todd Boulanger
Todd Boulanger
16 years ago

Some suggestions:
– figure C…perhaps clarifying the text on what type of pedestrain facilities the narrower section will be. (I am not sure the term \’shared\’ should be used if bikes are in a bike lane and it is onlt 8\’ wide.) And on the other side…perhaps the ped and bike figures should be displayed (segregated) similar to how the Hawthorne bridge has been recently laid out.

– how about a rehab option that is a hybrid…providing the wider upper level decks for peds and novice bicyclists PLUS the lower level bike commuter only section (fast traffic or reversible by time of day for in and out bound bike commuters).

– and the question of bike and ped access during construction is key…as a migitation how about making the access netork improvements first (so as to avoid car traffic construction detours) AND initiate a biek and ped ferry.

Matt Picio
16 years ago

Awesome and comprehensive story – thanks for the update, Jonathan!

It\’s nice to see that they actually incorporated all the input from the prior surveys and public meetings – most of the design options look decent. I look forward to seeing what 3 or so options they narrow down to for the SEIS.

a.O
a.O
16 years ago

Great piece, Jon.

As you know, I want no bridge. The livability of my neighborhood is reduced by so much motor vehicle traffic and I would like to see it go elsewhere. But at this point it\’s clear we\’re not ready to put cars in their rightful place, so as long as we only have two motor vehicle lanes on the bridge, I\’ll be satisfied.

Also, I think there is a fundamental fairness issue with Multnomah County tax payers paying for a bridge used mostly by Clackamas County residents. If we\’re going to build a new bridge (and apparently we are), I think there should be some cost sharing.

David Feldman
David Feldman
16 years ago

I don\’t live in Sellwood–or even in Portland–but I hope that the bridge does not expand beyond two automobile lanes. The Sellwood neighborhood has 19th century streets and buildings–how does anyone think that it can handle more car traffic? Rebuild Sellwood before it falls into the river, but also consider a second bridge, perhaps an enhanced West Linn-Oregon City bridge.

Tbird
Tbird
16 years ago

I\’d really like to see a model for replacement that shows:
1) A separated bike lane, a barrier from auto traffic.
and,
2) the bike lane to be wider than the ped lane. I think the models showing a 16\’ ped lane and 5 \’ bike lane are backward. Why should the 2-3 peds that walk across the bridge each day get such a wide space while bikes are STILL being relegated to last place.
I\’m glad the bridge is getting a proper replacement, but I am disappointed to see we are still looking at bike users as an after-thought instead of the primary concern. This is a great opportunity for Portland to make a bold statement that BIKES COME FIRST.

Martha R
Martha R
16 years ago

I second Tbird\’s suggestion that the bike lane be wider than the ped lane. A spacious bike lane with ample room for passing slower cyclists would be great.

Also, allowing bikes on the sidewalk while there are bike lanes will create confusion — peds will see the striped lanes and expect that all bikes will be (or should be) in the lane. That doesn\’t bode well for bike/ped interactions.

bicycledave
16 years ago

I commute across this bridge every day by bike and I wholeheartedly agree with a. O. that there should be no more than 2 auto lanes. Rush hour traffic on Tacoma is already saturated by the current two lane bridge. And remember, the traffic is further limited by the narrow width of the lanes and a weight limit. Even a new bridge limited to 2 lanes will feed more traffic onto Tacoma because larger trucks and Tri-met will be allowed back on the bridge.

Doug
Doug
16 years ago

I\’m disappointed that there doesn\’t seem to be much support for a transit only lane on the bridge. In order to help the city overall we need to think about more than what\’s best for us, I think making room for transit is going to be a key part of getting people out of their cars. In my opinion option D offers a good compromise between the needs of cyclists and non-cyclists.

rixtir
rixtir
16 years ago

The obvious solution would be to discourage inter-county commuters by keeping traffic speeds low on Tacoma, and and limiting it to two motor vehicle lanes.

Then hint broadly to Clackamas County that they need to lift their end….

DK
DK
16 years ago

Fix what\’s there, add wider sidewalks on both sides for peds. and bikes, and make the west side easily accessible without having to fear for your life!

VR
VR
16 years ago

DK:

You do realize that the Sellwood bridge is failing under it\’s own weight?

On top of that the west side piers are slowly sliding towards the river, putting even more stress on the failing parts of the approaches.

To \”fix what\’s there\” would probably cost more than building a whole new one, and would net us little in return.

NPbike
NPbike
16 years ago

The designs I\’ve seen actually look great for bike/ped, better than the hawthorne for sure. Just shows how far we\’ve come.

Re: Temporary bridge…how about the old Willamette River Water Taxi…could solve a lot of problems.

As for cantilevering, I suggest trying it on the fremont bridge first. Does anybody else desperately want this?